Land Use and Municipal Licenses to Develop in Los Cabos: What to Do if the Project Does Not Fit the Program
In Los Cabos there is no waiver for a project that does not fit the urban development program. You may have the site plan, the project you want to build on it and the capital ready, but land use and building licenses are granted by the municipality, and only in accordance with the urban development plans or programs that have been published and recorded. The Urban Development Law for the State of Baja California Sur (state; the Urban Development Law) says so in article 82: without conforming to those programs, “no authorization or license shall be granted.” If the project does not fit the land use, density or zoning of the parcel, two routes remain: adjust the project or request an amendment to the program, through a public procedure whose outcome the authority decides. What follows is that full route, in the order you will travel it, from the first document to request to what happens if you build outside the program.
Who decides and with what instrument
The Political Constitution of the United Mexican States (federal) empowers municipalities, in article 115, section V, items a, d and f, to “formulate, approve and administer municipal zoning and urban development plans,” authorize and control land use and “grant licenses and permits for construction.” The Urban Development Law brings that power down to the ground: town councils authorize the uses of areas and parcels, administer zoning and issue land use, construction, subdivision, tourism development and condominium licenses “in accordance with the urban development plans or programs” (article 13, sections II, III and X). The instrument, then, is the program. The authority that signs the license has no room to depart from it, which is why the useful question is not what the municipality thinks of your project, but what the program says about your parcel.
The applicable program and its term
It is the first document to request. Article 6 of the Urban Development Law subjects property rights to the urban development plans or programs “once they have been published and recorded in the Public Registry of Property and Commerce.” Municipal programs are published in the Official Bulletin of the State Government and recorded in the Public Registry within the following ten days, under articles 22 and 24 of the same law, and their term is indefinite under article 16. An indefinite term means the program does not lapse with time: it governs until amended through the procedure the law itself sets.
According to the Town Council’s list of regulations, San José del Cabo and Cabo San Lucas are governed by the Second Update of the Urban Development Master Plan San José del Cabo and Cabo San Lucas 2040, published in the Official Bulletin of the State Government on May 6, 2013. That fact is the starting point, not the end of the review. Its recording, the absence of a later version and the instrument applicable to a parcel outside those population centers are confirmed at the Public Registry and with the municipal authority. If the parcel falls outside, the question of which instrument governs it has to be answered before going further.
What zoning sets
With the program in hand, the next step is reading the zoning over your parcel. Zoning determines which uses and purposes are “permitted, prohibited or conditional,” the compatibility between uses, “population and construction densities” and risk zones, under article 56, sections III, V, VI and X bis, of the Urban Development Law. The law gives no figures: the densities of each zone are in the program and its maps, and they are stated only after reading them over the parcel. For you this has a very concrete consequence. The number of units or square meters the project promises does not come from the brochure or the preliminary design; it comes from that reading, and a financial model that does not start there is built on an assumption.
The sequence of authorizations
Prerequisites and the land use certificate
Before requesting land use or licenses, the Revenue Law for the Municipality of Los Cabos, Baja California Sur (municipal) requires in article 64 BIS proof that property tax is current, that the property is in the cadastre, that water and sanitation payments are current and that wastewater discharge meets the applicable parameters. These are four documents worth gathering before any other step, because without them the application does not start.
With those in order, the certificate comes next. Land use certificates are valid for three years to be exercised, and are deemed exercised when the applicant requests the construction start permit; if they expire unexercised, a new one is needed, under article 76 of the Urban Development Law. If you buy a parcel with a certificate already issued, look at the date first. A certificate more than three years old that was never exercised is of no use to you, and the new one will have to be requested against the program in force at that time, which may not be the one considered when the earlier one was issued.
Building license
To build, rebuild, enlarge or reconstruct in the municipality’s towns “prior license from the Competent Municipal Authority is required,” with an application signed by a licensed professional under the Construction Regulations for the State of Baja California Sur, under articles 78 and 79 of the municipal revenue law. Those regulations are state level, were published in the Official Bulletin of the State Government on April 20, 2005, and are applied by the municipal urban development department together with the state ministry in charge, under their articles 3 and 4; the Town Council’s list of regulations reports no municipal regulation of its own. Authorizations to start urbanization and building works are valid for two years, under article 76 of the Urban Development Law, and that period should be kept in mind when setting the construction start.
Subdivisions, condominiums and tourism developments
If the project is a subdivision, a condominium or a tourism development, the file grows. The application is filed by the owner and legal possessor, with recorded title and the property’s tax obligations current, and the municipal authority decides within thirty business days for subdivisions, condominiums or any urban development, under article 73 of the Urban Development Law. For subdivisions, condominiums and housing complexes, article 72 also requires water, sewage and electricity availability letters for the entire development. That the application is filed by the holder of recorded title means the process cannot be started in the name of someone who is not yet the registered owner.
For tourism and urban developments with regional or subregional impact, outside the limits of population centers or affecting beach accesses, the state urban planning ministry issues a technical opinion within fifteen business days, and the municipality authorizes if there is a favorable opinion or if none was issued within that period, under articles 12, section XV, and 69 of the Urban Development Law. If your project falls into any of those cases, the state opinion is one more stage of the timeline and should be identified from the start.
When the project does not fit the program
Adjusting the project
This is the moment that worries most, and the first way out is the most direct. If the authority denies the authorization or requests changes, it must notify the decision with its legal basis and reasons, and the applicant may correct the project and file the application again, under article 73 BIS of the same law. Those reasons are valuable: they tell you which part of the project conflicts with the program and therefore what needs to change. Before thinking about moving the program, it is prudent to ask whether the adjustment solves the problem, because it is the route that depends most on you.
Requesting an amendment to the program
If the adjustment is not enough, the program itself remains. Private parties “who prove their legitimate interest” may request in writing that the town council amend a plan or program, under article 43, section VI, of the Urban Development Law. The amendment follows the same procedure as approval, set in article 17: public notice and dissemination of the draft; a period of up to 120 calendar days with public hearings; an “objective and technical opinion” establishing that the amendment brings benefits to the municipality’s population and follows orderly long term planning; reasoned responses during consultation of up to 45 calendar days; and publication in the Official Bulletin and in two newspapers.
That procedure should be read for what it is. It is not a private arrangement between the developer and the municipality, but a public process, with hearings and consultation, whose opinion must establish benefits for the municipality’s population. The same article 17 provides that an amendment made without that procedure “shall be affected by absolute nullity,” and permits or licenses that contravene the programs have no effect, under article 99. A shortcut, in other words, does not amend the program, and a license that contravenes it has no effect. Whether legitimate interest is proven and whether the request can succeed is assessed case by case; the law does not allow it to be predicted.
Appeal against the decision
Decisions issued under the law may be challenged through a reconsideration appeal within the ten business days following notice, under articles 105 and 106 of the same law. It is a short period, which is why notice of a denial has to reach whoever will decide on the appeal immediately.
What happens if you build or sell outside the program
Anything built without a license or against the programs may be shut down, and it is demolished only when it cannot be regularized, with a technical opinion and a hearing for the affected party, under article 83 of the Urban Development Law. The sanctions in article 117 include closure, a fine “from five to one thousand times the daily value of the Unit of Measure and Update, or up to 10% of the commercial value of the property,” revocation of licenses and demolition at the offender’s cost. Put that percentage next to the value of your project and the risk stops being abstract: the fine can be measured against the commercial value of the property, not only in units of measure.
The risk also reaches the contract, and that matters both to whoever develops and to whoever buys units. Contracts on the use of parcels that contravene the programs have no effect, and the notary authorizes the deed only after verifying the certificates, authorizations or licenses, which are inserted or referenced in it, under articles 97 and 98 of the same law. Without those certificates, authorizations or licenses, the notary cannot authorize the deed, and a project marketed without them reaches the notary’s office without the documents the notary must verify.
Parcels in reserve areas or outside the urban footprint
If the parcel is in a reserve area under the programs, the State and the town council have a right of first refusal on its sale for value: they are notified of the amount and have up to thirty calendar days to exercise it, under article 64 of the Urban Development Law. For a buyer, that window is part of the closing timeline and should be anticipated in the promissory agreement.
Environmental review runs in parallel. The Law of Ecological Balance and Environmental Protection of the State of Baja California Sur (state) assigns to municipalities, in article 66, sections I and II, works linked to land use and construction and changes of use outside urban or reserve zones. It assigns to the State, in article 65, section III, real estate and tourism developments outside urban areas or reserves and outside coastal ecosystems, and in article 64 it excludes what article 28 of the General Law of Ecological Balance and Environmental Protection reserves to the Federation. Knowing which of the three authorities reviews your project is as important as knowing what the program says.
Frequently asked questions
Can the municipality grant a license to a project that does not fit the program?
No. The Urban Development Law provides that without conforming to the programs no authorization or license shall be granted, and permits that contravene them have no effect. The law provides no waiver.
How long is a land use certificate valid?
It is valid for three years to be exercised, and is deemed exercised when the construction start permit is requested. If it expires unexercised, a new one is needed.
Can I ask for the program to be amended?
Yes, if you prove legitimate interest, in writing before the town council. The amendment follows the same public procedure as approval, with hearings, a technical opinion and consultation, and its outcome is decided by the authority.
What happens if I build without a license?
The building may be shut down and, if it cannot be regularized, demolished with a technical opinion and a hearing for the affected party. Sanctions include a fine from five to one thousand times the daily value of the Unit of Measure and Update, or up to 10% of the commercial value of the property, and revocation of licenses.
Can I appeal a denial?
Decisions issued under the law may be challenged through a reconsideration appeal within the ten business days following notice.
How to start
Go back to the site plan you started with and answer four questions about it: which published and recorded program governs the parcel and what use, density and restrictions it assigns; whether there is a valid land use certificate and whether it has been exercised; whether the project needs a state opinion and which authority reviews the environmental impact; and whether the gap with the program is solved by adjusting the project or requires amending the program, and what timeline that implies. These questions do not replace reading the parcel’s file. The scope of our work in this area is set out in construction permits and land use.
For a specific project, you can request a complimentary initial assessment, subject to scope review. Contacting the firm does not create an attorney client relationship until the engagement is formalized in writing.
IBG Legal, headquartered in Cancún with an office in Mexico City, advises buyers and investors on real estate transactions and litigation, and handles matters in Los Cabos.
IBG Legal, your legal ally in Mexico. For any question about your investment or your property, contact us.
Sources and references
- Political Constitution of the United Mexican States (federal). Latest amendment DOF October 7, 2026. Article 115, section V, items a, d and f.
- Urban Development Law for the State of Baja California Sur (state). Latest amendment published in the BOGE on November 21, 2025, per the State Congress compilation. Articles 6; 12, section XV; 13, sections II, III and X; 16; 17; 22; 24; 43, section VI; 56, sections III, V, VI and X bis; 64; 69; 72; 73; 73 BIS; 76; 82; 83; 97; 98; 99; 105; 106 and 117.
- Revenue Law for the Municipality of Los Cabos, Baja California Sur (municipal). Latest amendment published in the BOGE on July 10, 2025, per the State Congress compilation. Articles 64 BIS, 78 and 79.
- Construction Regulations for the State of Baja California Sur (state). Published in BOGE No. 25 on April 20, 2005. Articles 3 and 4.
- Second Update of the Urban Development Master Plan San José del Cabo and Cabo San Lucas 2040 (municipal). Published in BOGE No. 19 Extraordinary on May 6, 2013.
- Town Council of Los Cabos, applicable regulations published on its transparency portal (section I, first quarter of 2026), https://transparencialoscabos.gob.mx/documentos/transparencia/PNT%202026/F1/F1.xlsx, consulted on October 9, 2026.
- Law of Ecological Balance and Environmental Protection of the State of Baja California Sur (state). Published in the BOGE on August 21, 2026; the State Congress compilation shows no amendments. Articles 64; 65, section III, and 66, sections I and II.
- General Law of Ecological Balance and Environmental Protection (federal). Latest amendment DOF January 19, 2026. Article 28 (only as an exclusion reference).

Discuss this matter
This article is for informational purposes only and does not imply that IBG Legal accepts matters outside its core practice areas.