Water and Utility Availability for Developments in Los Cabos: What to Review Before Investing
In Los Cabos, a subdivision, condominium or housing complex is not authorized without water, sewage and electricity availability letters for the entire development, which is why the availability letter the seller shows you weighs as much as the land deed. Article 72 of the Urban Development Law for the State of Baja California Sur (state) says so. The service is provided by a municipal operating agency that in turn depends on the national waters the Federation assigns to it, so rules from all three levels of government meet in a development’s water. Before buying, you need to know whether there is an availability letter that applies to that parcel and that project, what works it requires and who pays for them, and whether supply will come from the public network or from your own source, such as a well or a desalination plant. The answer depends on the parcel, the project and the documents the seller can produce. Start with the law that requires the paper.
What state law requires to authorize a development
The Urban Development Law for the State of Baja California Sur (the state Urban Development Law) requires those availability letters “for the entire development” in article 72. The phrase matters: availability is not measured against the first tower or the first phase, but against everything the project intends to be. If the parcel borders high risk zones identified in the urban development plans and programs, the developer also files a risk opinion, under the second paragraph of the same article. The application is filed before the municipal authority by whoever holds ownership and legal possession of the property, with the deed recorded in the cadastre and the Public Registry and proof that the parcel’s tax obligations are current, under article 73.
Two other rules of that law complete the picture. Urbanization may be done in phases, but article 77 requires each phase to leave the benefited areas “self sufficient in all their services.” A first phase, then, cannot rely on the water or sewage that will come with the second. And acts relating to subdivisions and condominiums carried out without the corresponding authorization are affected by absolute or relative nullity, under article 75. For whoever buys lots or units, that rule is what turns the lack of authorization into a problem of the purchase itself, not only of the developer.
What the law does not say about availability
This is where the letter you were shown starts raising questions. The law does not say who issues the availability letter, with what requirements, for how long it is valid or whether a new owner may use it; it only adds the requirements of the subdivision regulations, under article 72 of the state Urban Development Law itself. Those details are read in the document that grants it and confirmed with the authority that issued it. It is not wise to fill that silence with assumptions: a letter with no clear term, in someone else’s name or for a different project does not by itself answer the question that matters to you. The municipality’s urban development program is another instrument reviewed in each case.
Who provides the service in Los Cabos
The Political Constitution of the United Mexican States (federal) assigns to municipalities, in article 115, section III, item a), drinking water, drainage, sewerage and the treatment and disposal of wastewater. The Water Law of the State of Baja California Sur (state; the BCS Water Law) allows municipalities to provide those services through decentralized municipal operating agencies, under its articles 21 and 25, which exercise the planning, works, user registry and fee powers assigned by article 27. In Los Cabos, the Revenue Law for the Municipality of Los Cabos, Baja California Sur (state) names in article 64 BIS the “Municipal Operating Agency of the Drinking Water, Sewerage and Sanitation System of Los Cabos.” That is the counter you will deal with.
The agency, however, does not own the water. Municipal systems use national waters through a federal assignment, under articles 20 and 44 of the National Waters Law (federal), which takes mean annual availability into account, and article 22 of that law warns that titles “do not guarantee the existence or invariability of the volumes they cover.” At the local level, the provider may agree on restrictions in times of proven or foreseeable scarcity, with notice to users, under article 105 of the BCS Water Law. Read together, these rules say something worth keeping in mind when running the numbers: an availability letter does not turn supply into a guarantee, because neither does the federal title secure the volumes nor is local service safe from scarcity restrictions.
Municipal requirements tied to water
Before applying for building, lot layout, subdivision, merger, land use or completion licenses, the applicant must prove that property tax is current and present two certificates issued by the service provider: one showing that drinking water, sewerage and sanitation payments are current, and another showing that the parcel’s wastewater discharge meets the applicable parameters, under article 64 BIS of the Revenue Law for the Municipality of Los Cabos. Building or expanding desalination or treatment plants also requires authorization from the operating agency, under the last paragraph of the same article. For the file, this means that a water debt on the parcel is not the seller’s detail: without the corresponding certificate, licenses cannot be requested.
Infrastructure: who builds it and who pays
With the availability letter in hand, the next question is who pays for the works. Article 93 of the BCS Water Law provides that subdividers, urbanizers and developers build at their own cost the drinking water and sewerage installations and connections according to the project authorized by the municipal authority and the provider’s specifications; once in operation, those works become property of the operating agency or the municipality. They also cover the cost of the infrastructure the providers must build. For the investor, that rule translates into two budget lines: the development’s own networks and the share of the provider’s infrastructure it must cover. Neither should be left out of the financial model, and the contract should state who bears them.
In a condominium, each owner pays according to their meter and, in addition, their share of common consumption, for which all are jointly liable, under article 81 of the BCS Water Law. Joint liability means that common consumption left unpaid by one owner may be claimed from the others. The Law on the Condominium Property Regime of the State of Baja California Sur (state) allows the administrator, in article 47, to limit a delinquent owner’s water only if the condominium network has not been handed over to the operating agency. That is why it matters whether the networks have already been accepted or remain private: it determines what tools the administration has against an owner who does not pay.
Your own source: well, desalination plant or independent system
If the seller talks about a well or a desalination plant, the file changes. Article 77 of the BCS Water Law allows industrial, tourism, country and other productive developments to operate independent supply, desalination and wastewater removal systems, provided they have authorization from the service provider. That local authorization does not replace the federal one, and there are three federal fronts.
The first is the sea. Extracting seawater for desalination requires a concession, “including brackish water wells,” under article 17, second paragraph, of the National Waters Law, as amended in the DOF on December 11, 2025. A desalination plant fed by a brackish well, then, does not escape the concession just because it does not take water directly from the sea.
The second is the subsoil. Groundwater may be extracted freely unless the Federal Executive establishes a regulated, closed or reserve zone, or suspends or limits extraction by general agreement, under article 18 of the same law, and the exploitation, use or enjoyment of national waters by private parties is carried out through a concession under article 20. The National Water Commission agreement published in the DOF on November 9, 2023 reports negative mean annual availability in the Cabo San Lucas and San José del Cabo aquifers, and the Commission takes it into account when deciding new titles, under the first and second articles of the agreement. Which aquifer corresponds to the parcel and whether it is closed or regulated is confirmed with the Commission. A project that counts on a new well therefore depends on a decision in which that negative availability weighs, and it should not be taken as granted.
The third is discharge. Whoever discharges wastewater into the soil, subsoil or receiving bodies other than the municipal sewer needs a discharge permit; domestic discharges outside a municipal system require notice and compliance with the Mexican official standards, under article 44 of the National Waters Law. If the independent system includes wastewater removal outside the municipal sewer, that permit has to be on the same list as the concession.
Buying land that already has a well or water title
The water title offered with the land does not travel with the deed. Since the amendment published in the DOF on December 11, 2025, article 22 of the National Waters Law provides that “the rights covered by concessions and assignments shall not be subject to transfer.” When ownership of a property associated with a concession title is transferred, the water authority decides a reassignment and issues a new title in favor of whoever proves ownership, with the same volume, the same use and the remaining term, under article 37 BIS 1. What you acquire, in other words, is the property; the new title is issued by the authority. If the price includes a value for the water, that value depends on a reassignment the authority has yet to decide.
The second transitory article of the decree made that mechanism applicable one hundred eighty calendar days after publication and gave the National Water Commission six months to design the procedure, which must be decided in no more than 20 business days, under the same article 37 BIS 1. As of the date of this article, neither the procedure nor the amendment to the regulations was found in the DOF, so the requirements are confirmed with the Commission before closing. That confirmation is not optional: without it, nobody can tell you today which documents the reassignment will require.
If the property already has service from the agency, the owner is liable for the debts and the new owner is subrogated in the prior service contract, with notice to the provider within fifteen days, under article 98 of the BCS Water Law. Ask for the certificate of no debts before signing and put the notice on the closing calendar.
Frequently asked questions
Can a condominium be authorized without water availability?
No. The state Urban Development Law requires water, sewage and electricity availability for the entire development in subdivisions, condominiums and housing complexes.
Does an availability letter guarantee there will be water?
The law does not say so. Federal titles do not guarantee the existence or invariability of the volumes they cover, and the local provider may agree on restrictions in times of proven or foreseeable scarcity, with notice to users.
Who pays for the development’s water networks?
Subdividers, urbanizers and developers build at their own cost the installations and connections according to the authorized project and the provider’s specifications, and cover the cost of the infrastructure the providers must build. Once in operation, those works become property of the operating agency or the municipality.
Can I have my own well or desalination plant?
State law allows it for industrial, tourism, country and other productive developments, with authorization from the provider. Federal rules also apply: a concession to extract seawater for desalination, including brackish water wells; the rules on extraction and concession of groundwater; and a discharge permit or notice, as the case may be.
Does the land’s water title pass to the buyer?
Not through the deed. Concession rights are not subject to transfer; the water authority decides a reassignment and issues a new title in favor of whoever proves ownership, with the same volume, use and remaining term.
How to start
Go back to the letter you were shown and measure what it really covers with these questions. Whether there is an availability letter issued for this parcel and this project, who issued it, for what volume or units, with what conditions and term. Whether it is in the seller’s name and the buyer may use it, or whether it will have to be applied for again. What works and contributions the operating agency requires, and who bears them in the contract. If there is a well or a desalination plant, whether a federal concession, the agency’s authorization and a discharge permit exist, or at what stage they are. Whether the seller can produce the certificates of no debts and of discharge required by the municipal revenue law. And how the contract allocates the risk that availability is not obtained or comes with different conditions. These questions do not exhaust the review or guarantee the authorization, which the authority decides. Utility availability is part of our review of construction permits and land use.
If you are evaluating land or a project in Los Cabos, you can request a complimentary initial assessment, subject to scope review. Contacting the firm does not create an attorney client relationship until the engagement is formalized in writing.
IBG Legal, headquartered in Cancún with an office in Mexico City, advises buyers and investors on real estate transactions and litigation, and handles matters in Los Cabos.
IBG Legal, your legal ally in Mexico. For any question about your investment or your property, contact us.
Sources and references
- Political Constitution of the United Mexican States (federal). Latest amendment DOF October 7, 2026. Article 115, section III, item a).
- National Waters Law (federal). Latest amendment DOF December 11, 2025. Articles 17, 18, 20, 22, 37 BIS 1 and 44; second transitory article of the National Waters Law transitory provisions in the decree published in the DOF on December 11, 2025.
- Agreement updating the mean annual groundwater availability of the 653 aquifers of the United Mexican States, which form part of the hydrological administrative regions indicated (federal, National Water Commission). DOF November 9, 2023. First article (aquifers 0317 Cabo San Lucas and 0319 San José del Cabo) and second article.
- Water Law of the State of Baja California Sur (state). Latest amendment BOGE September 10, 2025, per the State Congress compilation. Articles 21, 25, 27, 77, 81, 93, 98 and 105.
- Urban Development Law for the State of Baja California Sur (state). Latest amendment BOGE November 21, 2025, per the State Congress compilation. Articles 72, 73, 75 and 77.
- Revenue Law for the Municipality of Los Cabos, Baja California Sur (state). Latest amendment BOGE July 10, 2025, per the State Congress compilation. Article 64 BIS.
- Law on the Condominium Property Regime of the State of Baja California Sur (state). Latest amendment BOGE October 31, 2016, per the State Congress compilation. Article 47.

Discuss this matter
This article is for informational purposes only and does not imply that IBG Legal accepts matters outside its core practice areas.